* 帖子主题 * 你是第 506 位浏览者 CG 军衔: PMU初级三星 财产: 经验: 魅力: 来自: 不告诉你 :) 鉴定: 本功能已经被关闭 发帖: 263篇 注册: 2002-2-5 -------------------------------------------------------------------------------- 1. Which one of the following statements regarding scope control is true? A) Scope control is used when changes may cause a project schedule or cost overrun. B) Scope control requires a formal change management process. C) Scope control is required on fixed price projects, but not on time and materials or cost-plus projects. D) Scope control prevents changes from occurring after requirements are defined. E) Scope control is the responsibility of the client. 2, In which one of the following project deliverables is the project manager's authority to apply resources typically documented? A) Requirements Traceability Matrix B) Project Charter C) Contract Terms and Conditions D) Cost Variance Report E) Work Breakdown Structure 3, Company XYZ has a fixed price contract to produce 10,000 widgets for a price of $100,000. An invoice will not be generated until all widgets are completed. The budgeted cost of manufacturing the widgets is $9 per widget. All widgets were to be completed by today. Unfortunately, the project is behind schedule, and only 9,000 widgets have been completed. Actual manufacturing costs to date are $90,000. In the sample scenario above, what is the cost performance index? A) 0 B) .9 C) 1 D) 1.1 E) 1.23 答案竟然是:A,E,D! -------------------------------------------------------------------------------- -------------------------------------------------------------------------------- [ 本文发表于 2002年6月19日 18:17:29 ] wuakq 军衔: 三等兵 财产: 经验: 魅力: 来自: 北京市 鉴定: 本功能已经被关闭 发帖: 153篇 注册: 2002-1-30 -------------------------------------------------------------------------------- 3 没有问题. AV = 9000 EV = 10000. --->CPI= 10000/9000 =1.1 EV是一个预算值. 原来的完工预算就是10000. 最后没有收到, 是另外一回事. -------------------------------------------------------------------------------- 明确目标, 不断积累. -------------------------------------------------------------------------------- [ 本文发表于 2002年6月19日 18:44:55 ] wuakq 军衔: 三等兵 财产: 经验: 魅力: 来自: 北京市 鉴定: 本功能已经被关闭 发帖: 153篇 注册: 2002-1-30 -------------------------------------------------------------------------------- 对不起, 上面的有错. 再看看. -------------------------------------------------------------------------------- 明确目标, 不断积累. -------------------------------------------------------------------------------- [ 本文发表于 2002年6月19日 18:54:38 ] polarbear 军衔: 二等兵 财产: 经验: 魅力: 来自: 北京 鉴定: 本功能已经被关闭 发帖: 140篇 注册: 2002-6-12 -------------------------------------------------------------------------------- 前两题,不知道, 第三题,我觉得应该是B 就是0.9, 1、到今天为止,生产9000个,AC=90000, 2、计划每个的成本是9,生产9000,EV=81000。 3、CPI=EV/AC=81000/90000=0.9 -------------------------------------------------------------------------------- I beleive I can fly, I beleive I can touch the sky! -------------------------------------------------------------------------------- [ 本文发表于 2002年6月20日 12:44:30 ] netxs 军衔: 三等兵 财产: 经验: 魅力: 来自: Beijing 鉴定: 本功能已经被关闭 发帖: 22篇 注册: 2001-11-26 -------------------------------------------------------------------------------- CG 在 2002-6-19 18:17:29 发表的内容 1. Which one of the following statements regarding scope control is true? A) Scope control is used when changes may cause a project schedule or cost overrun. B) Scope control requires a formal change management process. C) Scope control is required on fixed price projects, but not on time and materials or cost-plus projects. D) Scope control prevents changes from occurring after requirements are defined. E) Scope control is the responsibility of the client. 2, In which one of the following project deliverables is the project manager's authority to apply resources typically documented? A) Requirements Traceability Matrix B) Project Charter C) Contract Terms and Conditions D) Cost Variance Report E) Work Breakdown Structure 3, Company XYZ has a fixed price contract to produce 10,000 widgets for a price of $100,000. An invoice will not be generated until all widgets are completed. The budgeted cost of manufacturing the widgets is $9 per widget. All widgets were to be completed by today. Unfortunately, the project is behind schedule, and only 9,000 widgets have been completed. Actual manufacturing costs to date are $90,000. In the sample scenario above, what is the cost performance index? A) 0 B) .9 C) 1 D) 1.1 E) 1.23 答案竟然是:A,E,D! 1--D 2--B -------------------------------------------------------------------------------- -------------------------------------------------------------------------------- [ 本文发表于 2002年6月20日 13:08:03 ] netxs 军衔: 三等兵 财产: 经验: 魅力: 来自: Beijing 鉴定: 本功能已经被关闭 发帖: 22篇 注册: 2001-11-26 -------------------------------------------------------------------------------- 3--b 9000*9/90000=0.9 -------------------------------------------------------------------------------- -------------------------------------------------------------------------------- [ 本文发表于 2002年6月20日 13:12:59 ] 晓东 军衔: 三等兵 财产: 经验: 魅力: 来自: 不告诉你 :) 鉴定: 本功能已经被关闭 发帖: 70篇 注册: 2002-6-24 -------------------------------------------------------------------------------- 1-B,2-E,3-D。 第一题,范围变更一定造成进度或成本变更,但是造成进度或成本变更的变更不一定是范围变更,例如雇员辞职造成人手不够,雇员的涨工资要求得到满足等等。 第三题,BCWP=1000*9=9000; ACWP=900*9=8100; CPI=1.1 -------------------------------------------------------------------------------- 天道酬勤! -------------------------------------------------------------------------------- [ 本文发表于 2002年6月25日 9:37:44 ] CG 军衔: PMU初级三星 财产: 经验: 魅力: 来自: 不告诉你 :) 鉴定: 本功能已经被关闭 发帖: 263篇 注册: 2002-2-5 -------------------------------------------------------------------------------- 个人同意netxs的答案。 -------------------------------------------------------------------------------- -------------------------------------------------------------------------------- [ 本文发表于 2002年6月25日 17:54:44 ] jpgao 军衔: PMU初级一星 财产: 经验: 魅力: 来自: 北京市 鉴定: 本功能已经被关闭 发帖: 68篇 注册: 2002-7-5 -------------------------------------------------------------------------------- what mean about question #2? is B or E? is project charter belong to deliverables? -------------------------------------------------------------------------------- Continuous improvement -------------------------------------------------------------------------------- [ 本文发表于 2002年8月6日 8:21:53 ] helloxp 军衔: 三等兵 财产: 经验: 魅力: 来自: 不告诉你 :) 鉴定: 本功能已经被关闭 发帖: 26篇 注册: 2002-7-29 -------------------------------------------------------------------------------- I think the answer should be D,B,B -------------------------------------------------------------------------------- -------------------------------------------------------------------------------- [ 本文发表于 2002年8月6日 13:36:37 ] stonexu 军衔: PMU初级二星 财产: 经验: 魅力: 来自: 不告诉你 :) 鉴定: 本功能已经被关闭 发帖: 81篇 注册: 2002-5-10 -------------------------------------------------------------------------------- 1-A CDE都是错的,A和B相比,A更准确,计划和成本的超出都涉及了范围的变更,属于范围控制过程。 -------------------------------------------------------------------------------- -------------------------------------------------------------------------------- [ 本文发表于 2002年8月6日 15:11:50 ] yanxiaojing 军衔: 一等兵 财产: 经验: 魅力: 来自: 不告诉你 :) 鉴定: 本功能已经被关闭 发帖: 78篇 注册: 2001-11-26 -------------------------------------------------------------------------------- 1a -------------------------------------------------------------------------------- -------------------------------------------------------------------------------- [ 本文发表于 2002年8月7日 16:44:37 ] zhuangqianzhi 军衔: PMU初级一星 财产: 经验: 魅力: 来自: 不告诉你 :) 鉴定: 本功能已经被关闭 发帖: 58篇 注册: 2002-6-30 -------------------------------------------------------------------------------- 1、B范围变更需要正式程序 2、B 要注意看懂英文题目。项目经理利用资源的权利是在项目章程里面授予的。 3、B EV=90000 PV=100000 AC=81000 CPI=EV/AC=1.111111111 -------------------------------------------------------------------------------- -------------------------------------------------------------------------------- [ 本文发表于 2002年8月9日 9:09:17 ] DGHFX 军衔: PMU初级一星 财产: 经验: 魅力: 来自: 不告诉你 :) 鉴定: 本功能已经被关闭 发帖: 66篇 注册: 2001-12-8 -------------------------------------------------------------------------------- BBB(0.9) -------------------------------------------------------------------------------- -------------------------------------------------------------------------------- [ 本文发表于 2002年8月24日 9:39:31 ] zhuangqianzhi 军衔: PMU初级一星 财产: 经验: 魅力: 来自: 不告诉你 :) 鉴定: 本功能已经被关闭 发帖: 58篇 注册: 2002-6-30 -------------------------------------------------------------------------------- b b e -------------------------------------------------------------------------------- -------------------------------------------------------------------------------- [ 本文发表于 2002年8月31日 14:11:24 ] recall71 军衔: 三等兵 财产: 经验: 魅力: 来自: 不告诉你 :) 鉴定: 本功能已经被关闭 发帖: 34篇 注册: 2002-1-14 -------------------------------------------------------------------------------- 3d是对的 -------------------------------------------------------------------------------- -------------------------------------------------------------------------------- [ 本文发表于 2002年9月12日 16:31:54 ] ellen_yuan 军衔: 三等兵 财产: 经验: 魅力: 来自: 不告诉你 :) 鉴定: 本功能已经被关闭 发帖: 19篇 注册: 2002-8-1 -------------------------------------------------------------------------------- b e b -------------------------------------------------------------------------------- -------------------------------------------------------------------------------- [ 本文发表于 2002年9月13日 16:29:25 ] CG 军衔: PMU初级三星 财产: 经验: 魅力: 来自: 不告诉你 :) 鉴定: 本功能已经被关闭 发帖: 263篇 注册: 2002-2-5 -------------------------------------------------------------------------------- 1, B A- wrong. changes may require expanding the scope or may shrinking it. B- right. C,E - obviously wrong D- scope change control is concerned with managing change not preventing it. 2, B project charter provides the PM the authority to apply organizational resources to project activities. --see PMBOK p54. 3, B PV=$100,00 EV=$81,000 AC=$90,000 so, CPI=0.9 -------------------------------------------------------------------------------- -------------------------------------------------------------------------------- [ 本文发表于 2002年9月19日 14:55:10 ]
|