* 帖子主题 * 模拟考题二 你是第 675 位浏览者 zhutiefeng 军衔: PMU初级一星 财产: 经验: 魅力: 来自: 上海 鉴定: 本功能已经被关闭 发帖: 74篇 注册: 2001-12-31 -------------------------------------------------------------------------------- 20. You are remodeling your kitchen and decide to prepare a network diagram for this project. Your appliances must be purchased and available for installation by the time the cabinets are completed .In this example, these relationships are- a. Start to finish b. Finish to start c. Start to Start d. Finish to finish 21.To practice effective schedule control, your project team must be alert to any issues that may cause problems in the future. To best accomplish this, the team should- a. Review performance reports b. Allow no changes to the schedule c. Update the schedule management plan on a continuous basis d. Hold status reviews 22. You are working in a software development project. On this project, a number of tests must be performed, including some that must be performed multiple times. The project includes activities whose sequence is conditional based on the outcomes of prior activities. For example, if an error is discovered through inspection. The project’s design may have to be modified, creating the need for additional testing. The network technique best able to handle these situations is a- a. PSM network b. PERT chart c. GERT network d. XDM network 23. You have issued several revisions to your project’s schedule. In some cases, your schedule delays are now severe. To ensure accurate performance measurement information, you should- a. Issue a schedule update b. Rebaseline your schedule c. Rrepare a master schedule d. Initiate a change request 24. You are responsible for preparing a cost estimate for your project .Because you have been told to do the most accurate one possible, you decide to prepare a bottom-up estimate. Your first step is to- a. Locate a computerized tool to assist in the process b. Use the cost estimate from a previous project to help you prepare this estimate c. Identify and estimate the cost for each individual work item d. Consult with subject matter experts and use their suggestions as the basis for your estimate 25. When you review cost performance data on your project, different responses will be required depending on the degree of variance from the baseline. For example, a variance of 10% might not require immediate action, whereas a variance of 100% will require investigation. A description of how you plan to manage cost variances should be included in the- a. Cost management plan b. Change management plan c. Performance measurement plan d. Variance management plan 26. On your project, you need to assign costs to the time period in which they are incurred. To do this, you should- a. Identify the project components so that costs costs can be allocated b. Use the Project schedule as an input to cost budgeting c. Prepare a detailed and accurate cost estimate d. Prepare a cost performance plan 27.Each time you meet with your project sponsor, she emphasizes the need for cost control on your new e-business project. She always asks you about cost performance in terms of which budgets have been met and which have not. To answer her concerns, you should provide a. Performance reports b. Performance measurement graphs and charts c. Resource productivity analyses d. Trend analysis statistics 28. You receive a frantic phone call from your vice president who says she is going to meet with a prospective client in 15 minutes to discuss a large and complex “dot-com” project. She gives you a 30- second overview and asks you how much the project will cost. You quickly think of some similar past projects, factor in a few unknowns, and give her a number. What type of estimate did you just provide? a. Definitive b. Budget c. Order-of magnitude d. Detailed 29.You are managing an e-business project for a major consulting firm. The partner in charge is obsessed with earning as much profit as possible to increase his bonus. He Keeps asking you what the profit “numbers” are. Which of the following categories of profit is he really interested in? a. Operating b. Expected c. Gross d. Cumulative 30. Your approved cost baseline has changed because of a major scope change on your project. Your next step should be to- a. Estimate the magnitude of the scope change b. Issue a budget update c. Document lessons learned d. Execute the approved scope change 31. Your company has established a reward and recognition system for its project management professionals. Project cost performance is used as a criterion to criterion to determine rewards. What should you do to ensure that rewards reflect actual performance? a. Consider overtime work as part of the job. b. Prepare a cost baseline. c. Prepare a cost baseline. d. Estimate and budget controllable and uncontrollable costs separately. 32. You are the controller on your project. Your project manager has requested that you provide him with a forecast of project costs for the next 12 months. He needs this information to determine if the budget should be increased or decreased on this major construction project. In addition to the usual information sources, which of the following should you also consider! a. Cost estimates from similar projects b. The WBS c. Long-range weather forecasts d. Existing change requests 33.A forecast of total project costs based on project performance is provided by the- a. ETC b. CPI c. EAC d. TCPI 34.Recently, your company, a chicken-parts processor, had several health scares with regard to its products. These were isolated incidents that occurred in different geographic locations but over the same 3-weekperiod. The company has had no product safety concerns in the past and believes that there are no Problems with its inspection system. However, a new processing system was recently introduced. You were the project manager for this system and now have been asked to lead a team to investigate the situation and implement any needed changes. To help you analyze the new process, you and your team have decided to use which of the following techniques? a. System flowcharts b. Design of experiments c. Pareto analysis d. Control charts 35.Rank ordering of defects should be used to guide corrective action. This is the underlying principle behind- a. Trend analysis b. Inspections c. Control charts d. Pareto diagrams 36.Based on quality control measurements on your manufacturing project, management realizes that immediate corrective action is required to the material requirements planning (MRP) system to prevent future problems on other projects and to minimize rework. To implement the necessary changes you should follow- a. The organization’s quality policy b. The quality management plan c. Established operational definitions and procedures d. Procedures for overall change control 37.In order to monitor the number of errors or defects that have been identified and the number that remain undetected, you should- a. Design an experiment b. Use a checklist c. Conduct a trend ananlysis d. Perform an audit 38.Your quality assurance department recently performed a quality audit of your project and identified a number of findings and recommendations. One recommendation seems critical and should be implemented because it affects successful delivery of the product to your customer. If the recommendation is not implemented, the product sill not conform to requirements. You next Step should be to- a. Call a meeting of your project team to see who is responsible for the problem b. Reassign the team member who bad responsibility fir oversight of the problem c. Perform product rework immediately d. Issue a change request to implement the needed corrective action 39. Your company has embarked on a joint venture with three other firms, and you have won a major international contract to allow off- track betting in your client’s hotels. You have been appointed as project manager for this project. Your client recently won the Malcolm Baldridge award and emphasizes quality in all its endeavors. In addition to preparing a project plan, you contract calls for a separate project quality management plan to be prepared as a contract deliverable. You are working with your core team, which consists of employees from each firm in the joint venture, to develop this project quality management plan. Your first step in developing this plan is to- a. Determine specific metrics to use in the quality management process b. Identify the quality standards to use on the project c. Develop a quality policy for the project d. Identity specific quality management roles and responsibilities on the project 40. You recognize the importance of quality control on your project. However, you also know that quality control has costs associated with is and that the project has a limited budget. One way to reduce the cost of quality control is to- a. Work to ensure that the overall quality program is ISO compliant b. Use statistical sampling c. Conduct inspections throughout the process d. Use trend analysis -------------------------------------------------------------------------------- 峰峰 -------------------------------------------------------------------------------- [ 本文发表于 2002年6月20日 9:20:43 ] 云游 军衔: PMU初级一星 财产: 经验: 魅力: 来自: 武汉 鉴定: 本功能已经被关闭 发帖: 50篇 注册: 2002-5-19 -------------------------------------------------------------------------------- 20d 21a 22c 23b 24b 25a 26b 27a 28c 29? 30b 31d 32a 33b 34b 35d 36d 37b 38d 39a 40a 我猜的 -------------------------------------------------------------------------------- 善胜者不战,善战者不败,善败者不乱 -------------------------------------------------------------------------------- [ 本文发表于 2002年6月20日 23:53:49 ] laolu 军衔: 二等兵 财产: 经验: 魅力: 来自: 不告诉你 :) 鉴定: 本功能已经被关闭 发帖: 71篇 注册: 2002-5-1 -------------------------------------------------------------------------------- 外专局的题 -------------------------------------------------------------------------------- -------------------------------------------------------------------------------- [ 本文发表于 2002年6月21日 7:28:48 ] 一刀 头衔: 中士 军衔: PMU初级三星 财产: 经验: 魅力: 来自: 上海 鉴定: 本功能已经被关闭 发帖: 467篇 注册: 2002-4-13 -------------------------------------------------------------------------------- 随便看一下,40题应该是b。 -------------------------------------------------------------------------------- -------------------------------------------------------------------------------- [ 本文发表于 2002年6月21日 7:34:29 ] 一刀 头衔: 中士 军衔: PMU初级三星 财产: 经验: 魅力: 来自: 上海 鉴定: 本功能已经被关闭 发帖: 467篇 注册: 2002-4-13 -------------------------------------------------------------------------------- 29。c -------------------------------------------------------------------------------- -------------------------------------------------------------------------------- [ 本文发表于 2002年6月21日 8:04:03 ] 一刀 头衔: 中士 军衔: PMU初级三星 财产: 经验: 魅力: 来自: 上海 鉴定: 本功能已经被关闭 发帖: 467篇 注册: 2002-4-13 -------------------------------------------------------------------------------- 30.我觉得可能是c,因为baseline has changed,这里的baseline和budget是否是一回事? -------------------------------------------------------------------------------- -------------------------------------------------------------------------------- [ 本文发表于 2002年6月21日 8:08:05 ] 一刀 头衔: 中士 军衔: PMU初级三星 财产: 经验: 魅力: 来自: 上海 鉴定: 本功能已经被关闭 发帖: 467篇 注册: 2002-4-13 -------------------------------------------------------------------------------- 33.c -------------------------------------------------------------------------------- -------------------------------------------------------------------------------- [ 本文发表于 2002年6月21日 8:12:38 ] 一刀 头衔: 中士 军衔: PMU初级三星 财产: 经验: 魅力: 来自: 上海 鉴定: 本功能已经被关闭 发帖: 467篇 注册: 2002-4-13 -------------------------------------------------------------------------------- 37.c -------------------------------------------------------------------------------- -------------------------------------------------------------------------------- [ 本文发表于 2002年6月21日 8:20:36 ] 一刀 头衔: 中士 军衔: PMU初级三星 财产: 经验: 魅力: 来自: 上海 鉴定: 本功能已经被关闭 发帖: 467篇 注册: 2002-4-13 -------------------------------------------------------------------------------- 39.c -------------------------------------------------------------------------------- -------------------------------------------------------------------------------- [ 本文发表于 2002年6月21日 8:23:56 ] ralph 军衔: 三等兵 财产: 经验: 魅力: 来自: 深圳 鉴定: 本功能已经被关闭 发帖: 305篇 注册: 2002-3-5 -------------------------------------------------------------------------------- 30或许是b -------------------------------------------------------------------------------- -------------------------------------------------------------------------------- [ 本文发表于 2002年6月21日 8:51:20 ] 云游 军衔: PMU初级一星 财产: 经验: 魅力: 来自: 武汉 鉴定: 本功能已经被关闭 发帖: 50篇 注册: 2002-5-19 -------------------------------------------------------------------------------- 谁有标准答案,请发上来 -------------------------------------------------------------------------------- 善胜者不战,善战者不败,善败者不乱 -------------------------------------------------------------------------------- [ 本文发表于 2002年6月21日 17:23:31 ] laolu 军衔: 二等兵 财产: 经验: 魅力: 来自: 不告诉你 :) 鉴定: 本功能已经被关闭 发帖: 71篇 注册: 2002-5-1 -------------------------------------------------------------------------------- 24-c,29-a,32-d,33-c,34-d,40-b, 明天大家好运气。 -------------------------------------------------------------------------------- -------------------------------------------------------------------------------- [ 本文发表于 2002年6月21日 19:50:01 ] 晓东 军衔: 三等兵 财产: 经验: 魅力: 来自: 不告诉你 :) 鉴定: 本功能已经被关闭 发帖: 70篇 注册: 2002-6-24 -------------------------------------------------------------------------------- D/D/C/B/C/A/B/A/C/A/B/D/D/C/D/D/D/C/D/C/B -------------------------------------------------------------------------------- 天道酬勤! -------------------------------------------------------------------------------- [ 本文发表于 2002年6月25日 8:58:18 ] walkerch 军衔: PMU初级四星 财产: 经验: 魅力: 来自: 广东深圳市 鉴定: 本功能已经被关闭 发帖: 276篇 注册: 2002-3-12 -------------------------------------------------------------------------------- 有标准答案吗? -------------------------------------------------------------------------------- 西风啊,请吹响你嘹亮的号角。。。。。。。 -------------------------------------------------------------------------------- [ 本文发表于 2002年6月25日 17:43:01 ] jpgao 军衔: PMU初级一星 财产: 经验: 魅力: 来自: 北京市 鉴定: 本功能已经被关闭 发帖: 68篇 注册: 2002-7-5 -------------------------------------------------------------------------------- 第29题是什么意思? -------------------------------------------------------------------------------- Continuous improvement -------------------------------------------------------------------------------- [ 本文发表于 2002年8月7日 14:50:32 ] DGHFX 军衔: PMU初级一星 财产: 经验: 魅力: 来自: 不告诉你 :) 鉴定: 本功能已经被关闭 发帖: 66篇 注册: 2001-12-8 -------------------------------------------------------------------------------- DACBCCBBCDBDADBDDBDAB -------------------------------------------------------------------------------- -------------------------------------------------------------------------------- [ 本文发表于 2002年8月24日 10:23:53 ] zhutiefeng 军衔: PMU初级一星 财产: 经验: 魅力: 来自: 上海 鉴定: 本功能已经被关闭 发帖: 74篇 注册: 2001-12-31 -------------------------------------------------------------------------------- 新一版本项目管理资料光盘收集完成,有意购买的请联系 pmp@vip.81890.net oicq:1836142 -------------------------------------------------------------------------------- 峰峰 -------------------------------------------------------------------------------- [ 本文发表于 2002年11月20日 14:51:39 ]
|