jpgao 军衔: PMU初级一星 财产: 经验: 魅力: 来自: 北京市 鉴定: 本功能已经被关闭 发帖: 64篇 注册: 2002-7-5 -------------------------------------------------------------------------------- 1. To relate the functional organizations to the WBS, the project manager should use a- A. WBS index B. Project WBS C. Cost account matrix D. Work package assignment index The answer is C.没见过这词,以为与chart of account相近,是用来按劳动力,设备来分成本的。 D 为什么不对? 2.What is the technique of duration estimate where they analyze the allowances in activity sequence? A. dependency diagram B. Gantt chart C. Critical path D. PERT The answer is C. the allowances in activity sequence? 什么意思? 3. A project is out of control and you are replaced as a new project manager. You are asked to verify the quality level of the project and to take corrective action. What will you first do? A. Review the project plan B. Draw a control chart C. Have a brainstorming meeting D. Create a risk mitigation plan The answer is B. 我觉得是A. 项目失控,应该是已有结果,比如成本超支,进度拖后。应该看看计划,有多大差异和影响,如何更正。而control chart是看过程是否失控,我都知道失控了还看什么? 4. Written change orders should be required on- A. all project, large and small B. large projects C. Projects with a formal configuration management system in place D. Projects for which the cost of a change control system can be justified. The answer is A. 我怀疑答案,那口头变更什么时候用? -------------------------------------------------------------------------------- Continuous improvement -------------------------------------------------------------------------------- [ 本文发表于 2003年1月27日 15:35:34 ] walkerch 军衔: PMU初级四星 财产: 经验: 魅力: 来自: 广东深圳市 鉴定: 本功能已经被关闭 发帖: 276篇 注册: 2002-3-12 -------------------------------------------------------------------------------- 没时间,先解答两题较容易的吧。 2.指的是free float; 3.C-chart不单用于监控是否失控,出用于判断其失控的原因:是偶发性还是。。。; 4.书面与口头不相斥,口头与书面都用于所有项目啊。 -------------------------------------------------------------------------------- 西风啊,请吹响你嘹亮的号角。。。。。。。 -------------------------------------------------------------------------------- [ 本文发表于 2003年1月28日 11:15:02 ] bomber 军衔: PMU初级二星 财产: 经验: 魅力: 来自: 上海市 鉴定: 本功能已经被关闭 发帖: 128篇 注册: 2002-5-26 -------------------------------------------------------------------------------- 1. To relate the functional organizations to the WBS elements,the project manager should use a- a. WBS matrix b. WBS index c. Project WBS d. Cost account matrix e. Work package assignment index answer :d. Cost account matrix The cost account matrix is a one-page chart or conversion table that relates the functional organizations to the WBS elements.It lists the WBS elements horizontally across the top and the functional departments vertically in the left column.An X is placed where each organization has work to do in the WBS element.The cost account matrix provides a useful summary of the work contained in the WBS dictionary. -------------------------------------------------------------------------------- 有什么样的想法,就有什么样的未来 PMP -------------------------------------------------------------------------------- [ 本文发表于 2003年2月7日 21:34:38 ]
|